Foundation work almost complete!

Went over to the Bedford road construction site this morning and the foundation work is almost complete.  The major concrete action is done and I believe we are waiting for inspection.  Paul Hebert (my general contractor) and I finished (I … Continue reading

Posted in Construction progress, Deck House project 9961 | Tagged | Leave a comment

Blasting movie, site work and getting ready for the house foundation

In this prior post, you can see the site work prep for blasting of the rock ledge in order to prep it for the coming foundation – a rounded dome of hard rock with a 140 holes drilled into it … Continue reading

Posted in Construction progress, Deck House project 9961 | Tagged | Leave a comment

Happy Memorial day and photos of blasting prep

Beautiful day here in Carlisle today – cool (60’s) and windy.  Did some mowing, some roof rack prep on the cars, bought a dump sticker for my car, got gas for the tractor and dropped by Bedford Road to see … Continue reading

Posted in Construction progress, Deck House project 9961 | Tagged | Leave a comment

Marking out the house foundation and rock – LOTS of rock!

The prep stage for any project always seems longest – but it is where a project is made or broken.  This past week or so the foundation was marked out at my house site and then the last of the … Continue reading